You are here

Knott, Aleisha v Copeland Myrie

Court: 
Supreme Court
Catchwords: 

Breach of Contract-Whether the Defendant is liable for failing to complete the modification of the unfinished building-Whether the Claimant breached the contract for failing to pay the Defendant in a timely manner-Whether the Defendant is in breach of the contract for leaving the work site-Whether the Defendant should be compensated for additional works.

Document Type:

Year: 
2024
Suit/Claim number: 
2018CD00657
Neutral Citation: 
[2024] JMCC COMM. 5
Judge(s): 
Stephane Jackson-Haisley J.